Question
Identify five required post-installation tasks for Oracle Applications R12 E-Business Suite. (Choose five.)
Options
- ASet up a stage directory.
- BConfigure the client software.
- CReview security practices.
- DInstall the latest Java Development Kit.
- EUpdate the log and out PL/SQL directories.
- FConfigure database initialization parameters.
- GImplement product- and country-specific functionalities.