Oracle
1Z0-202 · Question #96
Whenever a new request for product information is entered by an agent, you want the system to immediately ship a brochure and close the request. You would implement a _____.
The correct answer is E. Workflow process triggered by a run-time event. See the full explanation below for the reasoning.
Question
Whenever a new request for product information is entered by an agent, you want the system to immediately ship a brochure and close the request. You would implement a _____.
Options
- AWorkflow policy column
- BWorkflow action
- CSiebel activity plan
- DSiebel assignment rule
- EWorkflow process triggered by a run-time event
How the community answered
(36 responses)- A3% (1)
- B3% (1)
- C14% (5)
- D6% (2)
- E75% (27)
Community Discussion
No community discussion yet for this question.