Which process requires the Process Supply Chain Orchestration Interface process to be executed manually so that a supply order gets created?
The correct answer is E. Min-Max planning replenishing a purchase request. Needs to be run manually for Inventory MINMAX.
Cost Management Cloud Overview
Question
Which process requires the Process Supply Chain Orchestration Interface process to be executed manually so that a supply order gets created?
Options
- APlanned Order Releases
- BDrop Shipment
- CBack-to-Back Procurement
- DBack-to-Back Contract Manufacturing
- EMin-Max planning replenishing a purchase request
How the community answered
(59 responses)- A14% (8)
- B2% (1)
- C3% (2)
- D8% (5)
- E73% (43)
Explanation
Needs to be run manually for Inventory MINMAX.
Topics
#supply chain orchestration interface#min-max planning#manual execution#purchase request