Which process requires the Process Supply Chain Orchestration Interface process to be executed manually so that a supply order gets created?

The correct answer is E. Min-Max planning replenishing a purchase request. Needs to be run manually for Inventory MINMAX.

Cost Management Cloud Overview

Question

Which process requires the Process Supply Chain Orchestration Interface process to be executed manually so that a supply order gets created?

Options

  • APlanned Order Releases
  • BDrop Shipment
  • CBack-to-Back Procurement
  • DBack-to-Back Contract Manufacturing
  • EMin-Max planning replenishing a purchase request

How the community answered

(59 responses)
  • A
    14% (8)
  • B
    2% (1)
  • C
    3% (2)
  • D
    8% (5)
  • E
    73% (43)

Explanation

Needs to be run manually for Inventory MINMAX.