Which four options apply to the "Lead Time" mode? (Choose four.)
The correct answer is A. Lead time can be specified in multiple ways. C. Calendars and transit time constraints are respected. D. No supply availability search is performed. E. The order promising engine does not generate any pegging. See the full explanation below for the reasoning.
Question
Which four options apply to the "Lead Time" mode? (Choose four.)
Options
- ALead time can be specified in multiple ways.
- BThe item is promised on the requested date irrespective of availability.
- CCalendars and transit time constraints are respected.
- DNo supply availability search is performed.
- EThe order promising engine does not generate any pegging.
How the community answered
(38 responses)- A76% (29)
- B24% (9)
Community Discussion