Oracle
1Z0-1077-22 · Question #16
Which process requires the Release Planning recommendation process to be executed manually so that a supply order gets created?
The correct answer is C. Back-to-Back Order. See the full explanation below for the reasoning.
Question
Which process requires the Release Planning recommendation process to be executed manually so that a supply order gets created?
Options
- AManual orders using File Based Data Load
- BMin-Max planning replenishing a transfer order
- CBack-to-Back Order
- DDrop Ship Order
- EMin-Max planning replenishing a purchase request
How the community answered
(24 responses)- B4% (1)
- C79% (19)
- D4% (1)
- E13% (3)
Community Discussion
No community discussion yet for this question.