You are configuring Landed Cost Management for client proof of concept and only want to set up required tasks. Which task must be completed?

The correct answer is B. Reference Types. Explanation/Reference:

Cost Accounting Setup

Question

You are configuring Landed Cost Management for client proof of concept and only want to set up required tasks. Which task must be completed?

Options

  • ACharge Name
  • BReference Types
  • CTrade Operation Templates
  • DRoutes
  • ETrade Operation

How the community answered

(22 responses)
  • A
    9% (2)
  • B
    82% (18)
  • C
    5% (1)
  • E
    5% (1)

Explanation

Explanation/Reference: