Which three actions need to be performed before attempting a data transfer service job?
The correct answer is A. Obtain an available host machine which can run the dts utility on-premise with SATA or USB C. Data Transfer Service and Storage Service Limits should be checked and raised if required. E. Create an object bucket to receive the job. See the full explanation below for the reasoning.
Question
Which three actions need to be performed before attempting a data transfer service job?
Options
- AObtain an available host machine which can run the dts utility on-premise with SATA or USB
- BGet access to a high-speed internet connection
- CData Transfer Service and Storage Service Limits should be checked and raised if required.
- DSet up SSH access to a host on OCI to coordinate the transfer job.
- ECreate an object bucket to receive the job.
How the community answered
(49 responses)- A78% (38)
- B8% (4)
- D14% (7)
Community Discussion