Which three actions are required to manually upgrade a database to Oracle Database 12c Release 2? (Choose three.)
The correct answer is A. Run the Pre-Upgrade information tool on the source database. See the full explanation below for the reasoning.
Question
Which three actions are required to manually upgrade a database to Oracle Database 12c Release 2? (Choose three.)
Options
- ARun the Pre-Upgrade information tool on the source database.
- BTake all user tablespaces offline before starting the upgrade.
- CCopy the network configuration files from the existing database home to the new Oracle home location.
- DRun the Parallel Upgrade utility from the new Oracle home.
- ERun Oracle Net Configuration Assistant (NETCA) to configure the listening protocol address and service information for the new release of Oracle Database.
- FMake all user tablespaces 'read only' before starting the upgrade.
- GStart the existing database in upgrade mode.
How the community answered
(55 responses)- A75% (41)
- B13% (7)
- C7% (4)
- D4% (2)
- E2% (1)