Identify three prerequisites for the successful installation of Oracle Grid Infrastructure 12c for a standard cluster when using Full Featured Grid Naming Service (GNS).

The correct answer is C. A DHCP service on the private network for the cluster is required to allocate virtual IP addresses E. DNS must be configured to delegate name resolution for the cluster subdomain to the cluster. F. A DHCP service on the public network for the cluster is required to allocate virtual IP addresses. See the full explanation below for the reasoning.

Question

Identify three prerequisites for the successful installation of Oracle Grid Infrastructure 12c for a standard cluster when using Full Featured Grid Naming Service (GNS).

Options

  • AYou must create a Grid Management Repository database.
  • BYou must enable the Name Server Cache Daemon (NSCD).
  • CA DHCP service on the private network for the cluster is required to allocate virtual IP addresses
  • DEach cluster node must have at least two network interface cards,
  • EDNS must be configured to delegate name resolution for the cluster subdomain to the cluster.
  • FA DHCP service on the public network for the cluster is required to allocate virtual IP addresses

How the community answered

(49 responses)
  • A
    12% (6)
  • B
    4% (2)
  • C
    80% (39)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.

Full 1Z0-068 Practice