1Z0-067 · Question #88
You create two Resource Manager plans, one for night time workloads, the other for day time. How would you make the plans switch automatically?
The correct answer is B. Use scheduler windows. The resource manager is only activated when a default resource plan is assigned. Only one resource plan can be active at any given time. Resource plan switches can be automated using scheduler windows or performed manually by setting the resource_manager_plan parameter using…
Question
You create two Resource Manager plans, one for night time workloads, the other for day time. How would you make the plans switch automatically?
Options
- AUse job classes.
- BUse scheduler windows.
- CUse the mapping rule for the consumer groups.
- DSet the switch_time plan directive for both plans.
- EUse scheduler schedules.
How the community answered
(57 responses)- A2% (1)
- B75% (43)
- C5% (3)
- D14% (8)
- E4% (2)
Explanation
The resource manager is only activated when a default resource plan is assigned. Only one resource plan can be active at any given time. Resource plan switches can be automated using scheduler windows or performed manually by setting the resource_manager_plan parameter using the alter system command as shown below.
Topics
Community Discussion
No community discussion yet for this question.