1Z0-062 · Question #284

Which four statements are true about the components of the Oracle Scheduler? (Choose four.)

The correct answer is B. A scheduler job can point to a chain instead of pointing to a single program object. C. A job may get started automatically when a window opens. F. A program can be used in the definition of multiple jobs. G. A program and schedule can be specified as part of a job definition. https://docs.oracle.com/cd/B19306_01/server.102/b14231/schedover.htm

Performing Database Maintenance

Question

Which four statements are true about the components of the Oracle Scheduler? (Choose four.)

Options

  • AA schedule can be specified to a single job only.
  • BA scheduler job can point to a chain instead of pointing to a single program object.
  • CA job may get started automatically when a window opens.
  • DA program and job can be specified as part of a schedule definition.
  • EA job is specified as part of a program specification.
  • FA program can be used in the definition of multiple jobs.
  • GA program and schedule can be specified as part of a job definition.

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    93% (28)
  • D
    3% (1)

Explanation

https://docs.oracle.com/cd/B19306_01/server.102/b14231/schedover.htm