Smith is a DBA with ABC Corp. He is in the process of tuning the database. He has received various problem statements from the customers. Identify three appropriately defined problem statements that…

The correct answer is D. The weekly backup took 30 minutes, and earlier it used to take 5 minutes. E. The batch process is taking 2 hours, whereas it should take only 30 minutes. F. The system currently has 100 users. See the full explanation below for the reasoning.

Question

Smith is a DBA with ABC Corp. He is in the process of tuning the database. He has received various problem statements from the customers. Identify three appropriately defined problem statements that Smith can use to tune the database correctly. (Choose three.)

Options

  • AThe system is too slow.
  • BOnline response is very slow.
  • CSometimes the batch process throws errors.
  • DThe weekly backup took 30 minutes, and earlier it used to take 5 minutes.
  • EThe batch process is taking 2 hours, whereas it should take only 30 minutes.
  • FThe system currently has 100 users.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    15% (4)
  • D
    73% (19)