Which statement is true while creating subplans using Resource Manager?
The correct answer is D. You can use a resource plan instead of a consumer group to implement a priority ranking within the plan. See the full explanation below for the reasoning.
Question
Which statement is true while creating subplans using Resource Manager?
Options
- AThe subplan must belong to the consumer group, SYS_GROUP.
- BThe total CPU usage at any given level must be less than 100%.
- CThe subplans can be used to restrict the degree of parallelism for a user.
- DYou can use a resource plan instead of a consumer group to implement a priority ranking within the plan.
How the community answered
(35 responses)- A3% (1)
- B6% (2)
- C9% (3)
- D83% (29)