Which statement is true regarding the creation of nested plans using Resource Manager?

The correct answer is E. Each nested plan gets a proportion of the CPU resources assigned to its parent group. See the full explanation below for the reasoning.

Question

Which statement is true regarding the creation of nested plans using Resource Manager?

Options

  • AOnly one nested subplan is allowed.
  • BThe plans can be nested up to four levels.
  • CResource Manager does not support nested plans.
  • DNested plans control only the degree of parallelism but not the CPUuuuu.
  • EEach nested plan gets a proportion of the CPU resources assigned to its parent group.

How the community answered

(16 responses)
  • B
    13% (2)
  • C
    6% (1)
  • E
    81% (13)