Which two actions should an administrator take to configure high availability in a Provisioning Server farm? (Choose two.)
The correct answer is A. Run the Configuration Wizard D. Choose up to four servers within the farm. See the full explanation below for the reasoning.
Question
Which two actions should an administrator take to configure high availability in a Provisioning Server farm? (Choose two.)
Options
- ARun the Configuration Wizard
- BEdit the target device properties
- CRestart the Streaming Service account
- DChoose up to four servers within the farm
How the community answered
(34 responses)- A71% (24)
- B18% (6)
- C12% (4)
Community Discussion