Scenario: A Citrix Engineer is managing a Provisioning Services Farm with the following specifications: - A single Farm with one Site, with two Provisioning Services servers deployed with 8 vCPU…
The correct answer is B. Add two additional Provisioning Services servers to the Site. See the full explanation below for the reasoning.
Question
Scenario: A Citrix Engineer is managing a Provisioning Services Farm with the following specifications:
- A single Farm with one Site, with two Provisioning Services servers
deployed with 8 vCPU each, which are supporting a total of 500 target devices in production.
- The ports and threads have been configured so that each server can
stream concurrently to 250 devices each.
- Due to an upcoming merger, 250 more target devices must be supported
by the existing Provisioning Services farm.
- The Provisioning Services servers must handle the extra capacity
while aligning to Citrix leading practices for resiliency. Which step should the engineer perform to accomplish these requirements?
Options
- AIsolate the Provisioning Services screaming traffic.
- BAdd two additional Provisioning Services servers to the Site.
- CMaintain the existing configurations for the environment.
- DAdd one additional Provisioning Services server to the Site.
How the community answered
(64 responses)- A9% (6)
- B72% (46)
- C5% (3)
- D14% (9)
Community Discussion
No community discussion yet for this question.