Which two steps should a Citrix Engineer perform to conduct a database failover test? (Choose two.)

The correct answer is B. Take the primary SQL database offline. D. Execute Get-BrokerServiceStatus on the Delivery Controller. See the full explanation below for the reasoning.

Question

Which two steps should a Citrix Engineer perform to conduct a database failover test? (Choose two.)

Options

  • ARestart the SQL Server.
  • BTake the primary SQL database offline.
  • CExecute Get-BrokerServiceStatus on the SQL Server.
  • DExecute Get-BrokerServiceStatus on the Delivery Controller.

How the community answered

(60 responses)
  • A
    13% (8)
  • B
    80% (48)
  • C
    7% (4)