Which two represent challenges that could be met by Data Center Virtualization? (Choose two.)

The correct answer is C. An organization's server team requires 1-2 hours of downtime for applications when performing D. An organization's server team requires 5 business days to provision a new server. See the full explanation below for the reasoning.

Question

Which two represent challenges that could be met by Data Center Virtualization? (Choose two.)

Options

  • AAn organization is reporting that it takes 24 hours to provision new desktops.
  • BAn organization is reporting that servers become unavailable for a short time during unplanned
  • CAn organization's server team requires 1-2 hours of downtime for applications when performing
  • DAn organization's server team requires 5 business days to provision a new server.

How the community answered

(41 responses)
  • A
    17% (7)
  • B
    7% (3)
  • C
    76% (31)