Due to high CPU workload on the Security Gateway, the security administrator decided to purchase a new multicore CPU to replace the existing single core CPU. After installation, is the administrator…

The correct answer is B. Go to clash-Run cpconfig|Configure CoreXL to make use of the additional Cores|Exit. See the full explanation below for the reasoning.

Question

Due to high CPU workload on the Security Gateway, the security administrator decided to purchase a new multicore CPU to replace the existing single core CPU. After installation, is the administrator required to perform any additional tasks?

Options

  • AGo to clash-Run cpstop|Run cpstart
  • BGo to clash-Run cpconfig|Configure CoreXL to make use of the additional Cores|Exit
  • CAdministrator does not need to perform any task. Check Point will make use of the newly installed
  • DGo to clash-Run cpconfig|Configure CoreXL to make use of the additional Cores|Exit

How the community answered

(58 responses)
  • A
    5% (3)
  • B
    74% (43)
  • C
    14% (8)
  • D
    7% (4)