MegaCorps' disaster recovery plan is past due for an update to the backup and restore section to enjoy the benefits of the new distributed R77 installation. You must propose a plan that meets the…
The correct answer is B. meets the required objective and both desired objectives. See the full explanation below for the reasoning.
Question
MegaCorps' disaster recovery plan is past due for an update to the backup and restore section to enjoy the benefits of the new distributed R77 installation. You must propose a plan that meets the following required and desired objectives:
- Required. Security Policy repository must be backed up no less
frequently than every 24 hours.
- Desired. Back up R77 components enforcing the Security Policies at
least once a week.
- Desired. Back up R77 logs at least once a week.
You develop a disaster recovery plan proposing the following:
- Use the utility cron to run the command upgrade_export each night on
the Security Management Servers.
- Configure the organization's routine backup software to back up files
created by the command upgrade_export.
- Configure GAiA back up utility to back up Security Gateways every
Saturday night.
- Use the utility cron to run the command upgrade_export each Saturday
night on the log servers.
- Configure an automatic, nightly logswitch.
- Configure the organization's routine back up software to back up the
switched logs every night. The corporate IT change review committee decides your plan:
Options
- Ameets the required objective and only one desired objective.
- Bmeets the required objective and both desired objectives.
- Cmeets therequiredobjective but does not meet eitherdesiredobjective.
- Ddoes not meet the required objective.
How the community answered
(20 responses)- A5% (1)
- B75% (15)
- C15% (3)
- D5% (1)