The correct answer is A. 1, 2, 4. See the full explanation below for the reasoning.
Question
In a R76 Management High Availability (HA) configuration, you can configure synchronization to occur automatically, when: 1. The Security Policy is installed. 2. The Security Policy is saved. 3. The Security Administrator logs in to the secondary Smart CenterServer, and changes its status to active. 4. A scheduled event occurs. 5. The user database is installed. Select the BEST response for the synchronization trigger.
Options
- A1, 2, 4
- B1, 2, 3, 4
- C1, 2, 5
- D1, 3, 4