For Management High Availability synchronization, what does the Advance status mean?

The correct answer is D. The peer SMS is more up-to-date. See the full explanation below for the reasoning.

Question

For Management High Availability synchronization, what does the Advance status mean?

Options

  • AThe peer SMS has not been synchronized properly.
  • BThe peer SMS is properly synchronized.
  • CThe active SMS and its peer have different installed policies and databases.
  • DThe peer SMS is more up-to-date.

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    14% (3)
  • D
    76% (16)