156-215.76 · Question #49
Your organization's disaster recovery plan needs an update to the backup and restore section to reap the new distributed R76 installation benefits. Your plan must meet the following required and…
The correct answer is C. Meets the required objective and both desired objectives. See the full explanation below for the reasoning.
Question
Your organization's disaster recovery plan needs an update to the backup and restore section to reap the new distributed R76 installation benefits. Your plan must meet the following required and desired objectives:
Required ObjectivE. The Security Policy repository must be backed up no less frequently than every 24 hours. Desired ObjectivE. The R76 components that enforce the Security Policies should be backed up at least once a week. Desired ObjectivE. Back up R76 logs at least once a week. Your disaster recovery plan is as follows:
- Use the cron utility to run the command upgrade_export each night on
the Security Management Servers.
- Configure the organization's routine back up software to back up the
files created by the command upgrade_export.
- Configure the GAiA back up utility to back up the Security Gateways
every Saturday night.
- Use the cron utility to run the command upgrade_export each Saturday
night on the log servers.
- Configure an automatic, nightly logswitch.
- Configure the organization's routine back up software to back up the
switched logs every night. Upon evaluation, your plan:
Options
- AMeets the required objective and only one desired objective.
- BMeets the required objective but does not meet either desired objective.
- CMeets the required objective and both desired objectives.
- DDoes not meet the required objective.
How the community answered
(25 responses)- A4% (1)
- B4% (1)
- C84% (21)
- D8% (2)
Community Discussion