Brocade
150-820 · Question #176
One of the switches in your Brocade VCS Fabric in logical chassis mode needs to be replaced. After configuring the replacement switch with the same VCS RBridge ID of the faulty switch, you attempt…
The correct answer is B. On the principal switch, you must enter the WWN of the replacement switch. D. On the principal switch, you need to run the vcs replace rbridge-id command. See the full explanation below for the reasoning.
Question
One of the switches in your Brocade VCS Fabric in logical chassis mode needs to be replaced. After configuring the replacement switch with the same VCS RBridge ID of the faulty switch, you attempt to replace the faulty switch with a new one but find the switch is segmented from the fabric. Which two steps should be completed to replace the faulty switch? (Choose two.)
Options
- AA copy of the principal switch configuration must be copied to the replacement switch.
- BOn the principal switch, you must enter the WWN of the replacement switch.
- CThe VCS RBridge ID of the replacement switch needs to be unique and cannot match the faulty
- DOn the principal switch, you need to run the vcs replace rbridge-id command.
How the community answered
(27 responses)- A7% (2)
- B70% (19)
- C22% (6)
Community Discussion
No community discussion yet for this question.