Brocade
143-130 · Question #47
You have a Teradata FICON device and FICON tape devices that must read/write to a remote data center that is 1000 km away connected using a DWDM link. Management requires that the link be nearly…
The correct answer is C. FCIP D. FICON Accelerator. See the full explanation below for the reasoning.
Question
You have a Teradata FICON device and FICON tape devices that must read/write to a remote data center that is 1000 km away connected using a DWDM link. Management requires that the link be nearly fully utilized. Which two technologies satisfy these requirements? (Choose two.)
Options
- AFC FastWrite (FC-FW)
- BFCIP FastWrite (FCIP-FW)
- CFCIP
- DFICON Accelerator
How the community answered
(18 responses)- A17% (3)
- B11% (2)
- C72% (13)
Community Discussion
No community discussion yet for this question.