143-130 · Question #36

You want to implement a Control Unit Port (CUP) and properly set up z/OS parameters for any Brocade DCX 8510 that processes FICON I/O. What are three results upon implementation? (Choose three.)

The correct answer is A. to provide RMF 74-7 records for RMF to use D. to enable updating of the FICON Director's time and date from z/OS E. to allow access to the Allow/Prohibit Matrix. See the full explanation below for the reasoning.

Question

You want to implement a Control Unit Port (CUP) and properly set up z/OS parameters for any Brocade DCX 8510 that processes FICON I/O. What are three results upon implementation? (Choose three.)

Options

  • Ato provide RMF 74-7 records for RMF to use
  • Bto use physical port 0xFE to communicate with z/OS
  • Cto facilitate the loading of firmware onto a FICON switching device
  • Dto enable updating of the FICON Director's time and date from z/OS
  • Eto allow access to the Allow/Prohibit Matrix

How the community answered

(51 responses)
  • A
    78% (40)
  • B
    14% (7)
  • C
    8% (4)