Which of the following resources would be measured for capacity planning? (Select TWO correct answers.)
The correct answer is A. CPU usage D. memory usage. See the full explanation below for the reasoning.
Question
Which of the following resources would be measured for capacity planning? (Select TWO correct answers.)
Options
- ACPU usage
- Bdisk usage
- Capplication load time
- Dmemory usage
How the community answered
(53 responses)- A74% (39)
- B8% (4)
- C19% (10)
Community Discussion