LPI
117-301 · Question #128
Which of the following resources would be measured for capacity planning? (Select TWO correct answers.)
The correct answer is B. disk I/O D. network I/O. See the full explanation below for the reasoning.
Question
Which of the following resources would be measured for capacity planning? (Select TWO correct answers.)
Options
- Avideo driver performance
- Bdisk I/O
- Csystem boot time
- Dnetwork I/O
How the community answered
(30 responses)- A17% (5)
- B73% (22)
- C10% (3)
Community Discussion
No community discussion yet for this question.