Which is a way of sustaining progress in the implementation of portfolio management?

The correct answer is C. Align reward and recognition processes for senior management to appropriate behaviours. Aligning reward and recognition processes to appropriate behaviours (C) sustains portfolio management progress because it creates lasting cultural and motivational change - when senior managers are incentivised to support portfolio practices, those practices become…

Understanding the principles upon which effective portfolio management is based

Question

Which is a way of sustaining progress in the implementation of portfolio management?

Options

  • AIntroduce completely new processes for portfolio management rather than trying to build on
  • BAdopt a big bang approach rather than an incremental or staged approach
  • CAlign reward and recognition processes for senior management to appropriate behaviours
  • DEnsure the organization uses the most sophisticated software solution available rather than

How the community answered

(48 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    88% (42)
  • D
    6% (3)

Explanation

Aligning reward and recognition processes to appropriate behaviours (C) sustains portfolio management progress because it creates lasting cultural and motivational change - when senior managers are incentivised to support portfolio practices, those practices become self-reinforcing rather than dependent on external pressure alone.

Why the distractors fail:

  • A is wrong because discarding existing processes ignores institutional knowledge and creates unnecessary disruption; building on what works is more sustainable.
  • B is wrong because a "big bang" approach carries high risk and resistance - incremental or staged rollouts allow learning, adjustment, and stakeholder buy-in along the way.
  • D is wrong because sophisticated software is only a tool; over-engineering the solution can create complexity and dependency without improving actual portfolio behaviours or outcomes.

Memory tip: Think "people before process, process before software" - lasting change in portfolio management is driven by human behaviour (rewards/recognition), then embedded in process, and only then supported by tools. If an answer points to technology or wholesale replacement as the primary driver, it's likely a distractor.