Question
Which is an example of a performance metric that can be used to assess the impact of portfolio management?
Options
- APercentage of milestones being achieved during a projects life cycle compared with the planned
- BThe successful delivery of linked projects and transformation activities to achieve an intended
- CPercentage increase in the number of customer complaints received during the implementation of
- DPercentage of initiatives delivered on time and/or budget compared within initial forecasts