106 · Question #36
Which is a main element of the management control practice?
The correct answer is C. Stage or phase gates. Stage or phase gates (C) are checkpoints embedded in a project or program lifecycle where work is formally reviewed and a decision is made to proceed, pause, or stop. They are a core mechanism of management control because they ensure oversight is applied at defined intervals…
Question
Which is a main element of the management control practice?
Options
- ADecision conferencing
- BBenefits eligibility rules
- CStage or phase gates
- DStrategy alignment
How the community answered
(25 responses)- A4% (1)
- C92% (23)
- D4% (1)
Explanation
Stage or phase gates (C) are checkpoints embedded in a project or program lifecycle where work is formally reviewed and a decision is made to proceed, pause, or stop. They are a core mechanism of management control because they ensure oversight is applied at defined intervals, preventing uncontrolled progression and enabling course correction.
A (Decision conferencing) is a facilitated group technique for reaching consensus on complex decisions - it's associated with portfolio prioritization, not management control's ongoing oversight function.
B (Benefits eligibility rules) belong to benefits management practice, governing when and how benefits can be claimed or measured - not a control mechanism over work execution.
D (Strategy alignment) is a concern of portfolio management and strategy management practices, which ensure initiatives support organizational direction - distinct from the operational control focus of management control.
Memory tip: Think of phase gates as "tollbooths" - work can't proceed down the road until it pays the toll (meets the criteria). If you see a question about controlling progress through a lifecycle, gates are your answer.