050-SEPROSIEM-01 · Question #11
Which document must be completed before a POC is approved?
The correct answer is C. Evaluation Agreement. An Evaluation Agreement must be signed and completed before a Proof of Concept can receive formal approval.
Question
Which document must be completed before a POC is approved?
Options
- APOC Project plan
- BPre-Install Checklist
- CEvaluation Agreement
- DPOC Approval Document
How the community answered
(36 responses)- A8% (3)
- B3% (1)
- C83% (30)
- D6% (2)
Why each option
An Evaluation Agreement must be signed and completed before a Proof of Concept can receive formal approval.
The POC Project Plan is developed as part of planning the POC execution, but it is not the prerequisite document required before approval is granted.
The Pre-Install Checklist is a technical readiness document used during the installation phase, not a prerequisite for POC approval.
The Evaluation Agreement is the formal contractual document that establishes the terms, scope, and expectations of a POC engagement. It must be completed prior to POC approval because it creates the legal and operational framework under which the POC is conducted, protecting both parties and defining success criteria.
A POC Approval Document is the output of the approval process, not a document that must be completed before approval is granted.
Concept tested: POC approval prerequisite documentation requirements